AI Power and Data-Center Bottlenecks
Grid connections are progressing toward delivered and operating data centers.
From power infrastructure to operating AI
- 1Power and permits
- 2Power construction
- 3Connection and energization
- 4Data center and servers
- 5Commissioning and delivery
- 6Operation
Will the planned buildout provide enough power?
2.26 + 5.20 = at least 7.46 GW planned generation → 5.00 GW compute assumed as IT load × PUE 1.30 = 6.50 GW required
The full planned capacity provides nominal headroom under these assumptions.
Change the assumptions
Resolution gates: plants complete → transmission connected → site demand and reserves covered
Project stages and sources →Project stages and capacity progress
No projects match these filters.
IREN Childress · Horizon
5 · Stage · Commissioning and deliveryHorizon 1 delivered
Polaris Forge 1
6 · Stage · Operation250 MW operational
Abilene Stargate
6 · Stage · OperationInitial buildings operating
Microsoft Fairwater
6 · Stage · OperationFirst facility operating
Meta Hyperion
1 · Stage · Power and permitsAdditional generation permits and data-center construction
Project Jupiter
1 · Stage · Power and permitsRevised power permit review
Nscale Narvik
4 · Stage · Data center and serversData-center construction and equipment preparation
AWS Salem · Susquehanna
1 · Stage · Power and permitsSupply agreement and grid transition
xAI Southaven · Power
2 · Stage · Power constructionPermanent power plant construction
Stargate UAE
4 · Stage · Data center and serversFirst cluster construction
IREN Sweetwater 1
3 · Stage · Connection and energizationHV substation energized
SK·AWS Ulsan AI Data Center
4 · Stage · Data center and serversData-center construction