IREN Sweetwater 1

Texas, US · Latest source 2026-09-08 · Last checked 2026-10-31

Current stageHV substation energized

  1. 1Power and permits
  2. 2Power construction
  3. 3Connection and energization
  4. 4Data center and servers
  5. 5Commissioning and delivery
  6. 6Operation
Grid-connected site power envelope1.4 GW
Next timingFirst 300 MW · Q4 2027 delivery target

Grid connection is complete; power delivery ramps with data-center construction and commissioning.

Update · 2026-10-31

IREN said in September 2026 that 300 MW (gross) of data center capacity is under construction at Sweetwater 1, targeting delivery in Q4 2027. The combined 2 GW Sweetwater Hub (Sweetwater 1 and 2) was conditionally included as Base Load in ERCOT’s Batch Zero process, subject to further approvals. Following substation energization in May 2026, the bottleneck has shifted to data center completion and commissioning.

The next bottleneck resolution gate

Data-center completion → server and cooling commissioning → customer delivery