Abilene Stargate

Texas, US · Latest source 2026-09-10 · Last checked 2026-10-31

Current stage6 of 8 buildings delivered (618 MW, 75%)

  1. 1Power and permits
  2. 2Power construction
  3. 3Connection and energization
  4. 4Data center and servers
  5. 5Commissioning and delivery
  6. 6Operation
Planned campus capacity1.2 GW
Next timingRemaining 2 buildings · timing not disclosed

The first two buildings were reported energized for AI training.

Update · 2026-10-31

Oracle said on its September 2026 earnings call that six of the eight Abilene campus buildings, representing 618 MW and 75% of total capacity, had been delivered to the customer. It delivered about 131,000 GPUs at the site in that quarter alone. Timing for the remaining two buildings was not disclosed. The 1.2 GW above is site power; IT capacity implied by 618 MW ÷ 75% is about 0.82 GW (derived).

The next bottleneck resolution gate

Energization and operation of the remaining two buildings

Sources

← All projects