Meta Hyperion

Louisiana, US · 2026-07-13

Current stageAdditional generation permits and data-center construction

  1. 1Power and permits
  2. 2Power construction
  3. 3Connection and energization
  4. 4Data center and servers
  5. 5Commissioning and delivery
  6. 6Operation
Seven additional planned gas plants>5.2 GW
Next timingPreviously approved plants · 2028–2029 targets

Additional generation and transmission buildout follows the previously approved 2.26 GW plan.

The next bottleneck resolution gate

Generation and transmission approvals and completion → load supply

Will the planned buildout provide enough power?

Hyperion · Capacity comparison after planned plant completion

Planned generation floor7.46 GW
Required power · assumed6.50 GW
Headroom · assumed+0.96 GW

2.26 + 5.20 = at least 7.46 GW planned generation → 5.00 GW compute assumed as IT load × PUE 1.30 = 6.50 GW required

The full planned capacity provides nominal headroom under these assumptions.

Assumes the 5 GW compute target is IT load after planned completion; before transmission constraints, net output and reserves.

Change the assumptions

Resolution gates: plants complete → transmission connected → site demand and reserves covered

Project stages and sources →

Sources