Meta Hyperion
Current stageAdditional generation permits and data-center construction
- 1Power and permits
- 2Power construction
- 3Connection and energization
- 4Data center and servers
- 5Commissioning and delivery
- 6Operation
Seven additional planned gas plants>5.2 GW
Next timingPreviously approved plants · 2028–2029 targets
Additional generation and transmission buildout follows the previously approved 2.26 GW plan.
The next bottleneck resolution gate
Generation and transmission approvals and completion → load supply
Will the planned buildout provide enough power?
Planned generation floor7.46 GW
Required power · assumed6.50 GW
Headroom · assumed+0.96 GW
2.26 + 5.20 = at least 7.46 GW planned generation → 5.00 GW compute assumed as IT load × PUE 1.30 = 6.50 GW required
The full planned capacity provides nominal headroom under these assumptions.
Change the assumptions
Resolution gates: plants complete → transmission connected → site demand and reserves covered
Project stages and sources →