IREN Childress · Horizon
Current stageHorizon 1 delivered
- 1Power and permits
- 2Power construction
- 3Connection and energization
- 4Data center and servers
- 5Commissioning and delivery
- 6Operation
IT delivery target0.200 GW
Next timingQ4 2026 · subsequent delivery target
25%Delivered capacity · 50 / 200 MW IT
After delivery of 50 MW, another 150 MW remains.
The next bottleneck resolution gate
Horizon 2 commissioning and Horizon 3–4 delivery