SK·AWS Ulsan AI Data Center

Ulsan, South Korea · Latest source 2026-09-13 · Last checked 2026-10-31

Current stageData-center construction

  1. 1Power and permits
  2. 2Power construction
  3. 3Connection and energization
  4. 4Data center and servers
  5. 5Commissioning and delivery
  6. 6Operation
First-phase capacity0.103 GW
Next timing2H 2027 · operation target

Power supply and commissioning are the next gates for operation in Ulsan.

Update · 2026-10-31

SK Telecom is building an approximately 103 MW hyperscale AI data center in Ulsan with AWS, targeting operation in the second half of 2027 (July 2026). SK is pursuing expansion of the Ulsan hub to over 1 GW, and Chairman Chey Tae-won said in September 2026 that talks on an additional 900 MW were well advanced. The expansion has not been finalized; power supply and commissioning of the first facility remain the next gates.

The next bottleneck resolution gate

Power supply → equipment commissioning → operation