Stargate UAE

UAE · Latest source 2026-09-11 · Last checked 2026-10-31

Current stageFirst cluster construction

  1. 1Power and permits
  2. 2Power construction
  3. 3Connection and energization
  4. 4Data center and servers
  5. 5Commissioning and delivery
  6. 6Operation
Initial-phase target0.200 GW
Next timingQ3 2026 target · start not announced

The initial 0.200 GW is the first operating phase of the 1 GW plan.

Update · 2026-10-31

The first 200 MW of Stargate UAE was targeted for completion in Q3 2026, and in August 2026 two 100 MW buildings were reported enclosed with interior fit-out under way. Reuters reported in September 2026 that the UAE is reviewing a more distributed design for the wider 5 GW campus after Iranian attacks, while the first phase proceeds with added protection. As of end-October 2026, no official energization or operation of the first cluster had been announced.

The next bottleneck resolution gate

Initial cluster energization and operation

Sources

← All projects