AWS Salem · Susquehanna
Current stageGrid transition completed (Apr 2026)
- 1Power and permits
- 2Power construction
- 3Connection and energization
- 4Data center and servers
- 5Commissioning and delivery
- 6Operation
Contract ceiling across multiple sites1.920 GW
Next timingPhased ramp to full volume by 2032
The agreement can supply multiple AWS sites in Pennsylvania.
Update · 2026-10-31
Talen Energy disclosed in its 10-Q filings that power supply from Susquehanna to AWS moved to the revised front-of-the-meter PPA in April 2026. The contract ceiling is unchanged at up to 1,920 MW through 2042, with deliveries ramping to full volume no later than 2032. With the transition completed alongside the Unit 1 refueling outage (March 23–May 4, 2026), the next gate is the phased ramp of contracted volume rather than the grid transition itself.
The next bottleneck resolution gate
Phased delivery of contracted volume (full volume by 2032)