Polaris Forge 1

North Dakota, US · 2026-10-02

Current stage250 MW operational

  1. 1Power and permits
  2. 2Power construction
  3. 3Connection and energization
  4. 4Data center and servers
  5. 5Commissioning and delivery
  6. 6Operation
Critical IT target0.400 GW
Next timingRemaining buildout
62.5%Operating capacity · 250 / 400 MW IT
62.5%

Operational capacity reached 250 MW, or 62.5% of contracted capacity.

The next bottleneck resolution gate

Delivery and operation of the remaining 150 MW

Sources